CONSTRUCTION OF SEWER SYSTEM OF ORTAKOY

Our completed project consists of works such as totally 132.213 meter steam cured concrete and reinforced concrete pipe with 200 – 800 meter diameters, constructions of sewerage network and collector lines, manholes and parcel manholes. EMPLOYER İLLER BANKASI GENEL MÜDÜRLÜĞÜ /ANKARA

[ More → ]
emet2

PICKLING OF EMET HISARCIK

Our completed project consists of works such as excavating and crushing of 5.000.000 m³ pickling rock at the boron site of Eti Mine, loading, transporting to the dump site and constructing and maintenance works of site roads. EMPLOYER ETİ MADEN İŞLETMELERİ GENEL MÜDÜRLÜĞÜ / EMET BOR İŞLETME MÜDÜRLÜĞÜ

[ More → ]
bilecik1

1st SECTION POTABLE WATER LINE CONSTRUCTION OF BILECIK

Our completed drinking water project consists of works such as totally 24.404 meter CTP and steel pipe in 900 mm diameter, 9.400 meter transmission line made of steel pipe, 2 units of 50 m² and 1 unit of 200 m² tanks, elevation centre with 2 groups, drainage system, vane chamber, emptying and vacuum lifter. EMPLOYER [...]

[ More → ]
vanyol1

CONSTRUCTION OF HIGHWAY OF TATVAN – VAN

Our project completed on Provincial Border of Van – Tatvan State Highway is 10 kilometers long. Project covers earth works, works of art, plant-mix sub base, base works etc. EMPLOYER KARAYOLLARI 11. BÖLGE MÜDÜRLÜĞÜ

[ More → ]
sari1

CONSTRUCTION OF SEWERAGE OF SARIYAHSI

Our completed project consists of works such as totally 60.500 meter steam cured concrete and reinforced concrete pipe, constructions of sewerage network and collector lines, manholes and parcel manhole connections producing. EMPLOYER İLLER BANKASI GENEL MÜDÜRLÜĞÜ /ANKARA

[ More → ]
murat2

MURAT BRIDGE OF MUS

The bridge construction completed on border road of 8th Region of Mus has 8 spans and is 142 meters long. Bridge was constructed with bored pile and pre-stressed beam carrier system.

[ More → ]
ahlat1

POTABLE WATER LINE CONSTRUCTION OF AHLAT-BITLIS

Our completed project consists of works such as totally 3.500 meter transmission line of drinking water through steel pipe in  400 mm diameter, building of elevation centre with five groups, one piece of 5000 m³ reinforced concrete tank, and procurement of pump. 7000 m³ excavation works are realized for the project.

[ More → ]
guzelkonk1

GUZELKONAK BRIDGES ON TATVAN HIGHWAY

The project completed at Tatvan – Van State Highway is the work of constructing bridges of Guzelkonak Group (Guzelkonak and Sapur). Guzelkonak Bridge km: 61+600 Sapur Bridge km: 131+300 EMPLOYER KARAYOLLARI 11. BÖLGE MÜDÜRLÜĞÜ